What a Fixed-Price Custom-Home Contract Actually Guarantees (and What It Never Can)

Quick answer: A fixed-price contract guarantees the price of the house described in the plans, specifications and selections you sign. It does not guarantee the price of anything not yet defined: allowance items, changes you request, conditions nobody could see in the ground, or terms the contract itself carves out, such as escalation clauses. Read those parts closely.

"Fixed price" and "no surprises" are popular promises around Buford, and for good reason: nobody wants an open-ended bill. A fixed price is a real protection, but it is a promise about a defined scope of work, not every dollar you will spend. Here is what it covers, what it cannot, and where the price can still move.

This article is general information, not legal advice. For questions about a specific contract, talk to a Georgia real estate or construction attorney.

What is a fixed-price contract?

A fixed-price contract sets one price for a defined house. The builder estimates labor, materials, overhead and profit, adds a cushion for risk, and agrees to build the plans and specifications for that number. As Consumer Reports explains, if costs run over for a foreseeable reason, such as a quantity the builder underestimated, the builder absorbs it.

What does a fixed price cover, and what does it not?

The fixed price covers the work the documents describe. Anything the documents leave open, or that changes after signing, sits outside it.

Usually covered by the fixed priceUsually not covered, or only partly
The house as drawn in the signed plansChanges you request after signing
Materials and methods named in the specificationsUpgrades beyond an allowance
Selections finalized before signingSelections still listed as allowances
The builder's estimating mistakes on defined workRock, buried debris, poor soil or water found during digging, if the contract excludes them
Labor and subcontractor costs for defined workMaterial price jumps, if the contract has an escalation clause
Permits and fees the contract listsChanges required by an inspector or code change after signing, depending on the contract
Overhead and the builder's profitItems the contract names as owner-supplied or excluded

How does a fixed price compare with cost-plus?

Under cost-plus, you pay actual costs plus an agreed fee. Consumer Reports notes that most cost-plus contracts include a guaranteed maximum price that caps the total, and that the homeowner keeps the savings if the project comes in under budget, but needs to watch the paperwork closely.

FactorFixed priceCost-plus
Who carries overrun risk on defined workThe builderMostly the owner, unless there is a cap
What you seeThe total priceInvoices and receipts
Savings if costs come in lowUsually kept by the builderUsually kept by the owner
How the price is builtIncludes a cushion for riskActual cost plus a fee
Best forA plan and selections largely settled before signingOwners who want flexibility and transparency

How do change orders affect a fixed price?

A change order is a signed amendment that adds, removes or changes work, and it adjusts the price and often the schedule. It is the normal, honest way a fixed price moves. A good change order states:

  • what is changing, in enough detail to build from;
  • the price increase or credit;
  • any effect on the completion date;
  • signatures from both owner and builder before the work is done.

Verbal changes are where most disputes start. The Georgia Attorney General's Consumer Protection Division advises getting all guarantees, warranties and promises in writing.

Kitchen sink run with apron-front sink and lantern pendant — Shadburn Ferry, a custom home built by Ironwood Construction Group in Buford, Georgia.

How do allowances fit into a fixed price?

An allowance is a placeholder budget for something not yet chosen, such as light fixtures or countertops. The allowance is part of the fixed price, but your final choice may cost more or less. If you go over, you pay the difference; if you come in under, the contract decides whether you get a credit and how much (NewHomeSource). The more selections you finalize before signing, the more of your price is truly fixed. Our guide to selections without a showroom walks through that process.

What about unforeseen site conditions?

No builder can fully price what nobody can see underground. Rock, buried debris, soft soil or springs can turn up once excavation starts. Contracts handle this in different ways:

  • the builder includes a set amount of excavation or rock removal, with extra work priced by change order;
  • the contract excludes hidden conditions and prices them as they arise;
  • the owner pays for soil testing or engineering up front to reduce the unknowns.

None of these is wrong. What matters is that the contract says which one applies.

What is an escalation clause?

An escalation clause lets the price rise if specific material or labor costs go up by more than a stated amount before they are bought. If your contract has one, check what triggers it, which items it covers, how the increase is proven, whether there is a cap, and whether prices that fall bring you a credit.

What Georgia law points should you know?

A few Georgia rules show up in or around every residential building contract.

  1. Right to Repair Act notice. Georgia's Right to Repair Act, O.C.G.A. Section 8-2-35 and following, requires homeowners to give a contractor written notice of a construction defect claim at least 90 days before filing suit, and gives the contractor a chance to inspect and offer a repair or payment (Georgia Consumer Protection Division). Under O.C.G.A. Section 8-2-41, a contractor who contracts to build a home must give the owner conspicuous notice of this process, and it may be included in the contract. Expect to see it.
  2. Lien rights. Contractors, subcontractors and suppliers who are not paid can file a claim of lien against the property, generally within 90 days after completing their work or furnishing materials, under O.C.G.A. Section 44-14-361.1. That is why owners and lenders ask for lien waivers with each draw payment.
  3. Lien waiver forms. Georgia uses statutory lien waiver forms under O.C.G.A. Section 44-14-366, which were amended effective January 1, 2021 (Morris, Manning & Martin). Ask your builder how waivers are collected.
  4. Pay for completed work. The Consumer Protection Division recommends tying payments to completed stages of the job and being wary of paying for unfinished work.

The wrong way vs. the right way to read a fixed-price contract

Most price surprises were written into the contract before anyone broke ground.

The wrong wayThe right way
Comparing builders by the bottom-line number aloneComparing what each price includes, line by line
Assuming every allowance fits the home you wantListing each allowance and testing it against real choices
Skimming past the site conditions clauseAsking what excavation or rock work is included, and how extra is priced
Missing an escalation clauseReading its triggers, the items it covers and any cap
Agreeing to changes in a conversation on siteSigning a change order with price and schedule before the work is done
Paying ahead of the workTying each payment to a completed stage, with lien waivers

Advantages of each contract type

Advantages of a fixed price

  • You know the price of the defined house before construction starts.
  • The builder carries the risk of its own estimating mistakes on defined work.
  • Your lender and your budget work from one firm number.
  • There are fewer invoices to review during the build.

Advantages of cost-plus

  • You see the real invoices and receipts, so the books are open.
  • If costs come in low, the savings usually stay with you.
  • The price is not padded with a cushion for the builder's risk.
  • It handles a plan still taking shape more easily, and a guaranteed maximum price can cap the total.

When to do what

  1. Before you ask for a price: settle the plan and as many selections as you can, so more of the price is truly fixed.
  2. Before you sign: list every allowance, read the site conditions, escalation and change order clauses, and confirm the builder's license on the Georgia Secretary of State lookup.
  3. Before excavation: decide whether soil testing or engineering is worth doing to reduce the unknowns underground.
  4. During the build: put every change in a signed change order before the work is done.
  5. At each draw: pay for completed stages and collect lien waivers.

How Ironwood approaches contracts

Ironwood Construction Group is a family-owned builder, Clay Ortiz and his son Levi, building custom homes in Buford, Sugar Hill and across north Gwinnett and Hall County since July 2008. We hold Georgia residential-light commercial license RLCO003511. You talk to the builder directly, so you can ask exactly what your price includes and get a straight answer. Talk to the builder before you sign anything, with us or anyone else.

Frequently asked questions about fixed-price home contracts

Does a fixed price mean my final cost cannot change?

No. It means the price of the defined work is set. Change orders, allowance overages and excluded conditions can still change what you pay.

Is fixed price better than cost-plus?

Neither is always better. Fixed price suits a settled plan; cost-plus suits owners who want open books and flexibility.

Can a builder raise a fixed price for material costs?

Only if the contract allows it, usually through an escalation clause. Without one, material price increases on defined work are generally the builder's risk.

What is the Right to Repair Act notice in my contract?

It explains Georgia's pre-suit process for construction defects: the owner sends written notice at least 90 days before suing, and the builder may inspect and offer to repair or pay.

Should a lawyer review my building contract?

It is a good idea for a purchase this size. This article is general information, not legal advice.

Sources

  • Consumer Reports, "Know What Type of Remodeling Contract You're Signing," May 2, 2016
  • NewHomeSource, "What to Know About Builder Allowances," March 14, 2025
  • Georgia Attorney General Consumer Protection Division, "Right to Repair Act," consumer.georgia.gov
  • Georgia Attorney General Consumer Protection Division, Home Building and Home Repairs/Improvements, consumer.georgia.gov
  • O.C.G.A. Section 8-2-41, Notice to consumer required, via Justia (2025 Code of Georgia)
  • O.C.G.A. Section 44-14-361.1, Perfection of liens, via Justia
  • Morris, Manning & Martin, "If You Don't Like the Law, Change It: Georgia Lien Waiver Statute and Statutory Lien Waiver Forms Amended," August 6, 2020